POWER

Groundwork : FLINTSHIRE BRIDGE

Client : Siemens PLC

 

Project: Groundwork : Flintshire Bridge, Flint

 

Project  Value: £4.2m

Groundwork : Flintshire Bridge, Flint

 

Lowbury construction have been on-site working on numerous projects at Flintshire Bridge since 2013 to-date 2018.

 

Project scope was to clear the existing land of underground obstructions, in particular 2000m3 of heavily reinforced concrete, remove unsuitable surface material and form the main future works compound and formation by moving approx. 250,000m3 of material around to the required areas of site, compacting the material using an dynamic compacting machine and subsequently testing the compaction. The site had trace elements of asbestos and as such air monitoring was continually check.

 

Formation of new contractors car park which involved earthworks, kerbing, surfacing and line marking • New surface water mains brought onto site • Foul drainage associated with the new welfare and office facility • The enabling works were undertaken successfully prior to the commencement of the main contractor

We are currently back on site undertaking finishing and demobilization works which includes foundation bases in the live substation, grouting, surfacing, fencing, structural steelwork, cladding

The first phased project consisted of major site establishment & preparation works.

 

Images above show larger scales cutting and carving works, together with specialist vibro compacting equipment for preparation of the main land remediation.

 

Lowbury Construction Limited, The Old Police Station, 658-662 Liverpool Road, Cadishead, Manchester, M44 5AD, Tel:   0161 775 4376, Fax: 0161 777 9482, Email: admin@lowbury.co.uk